WINTER UPDATE—DECEMBER 27, 2011
What's Happening Right Now
Construction along our stretch of University Avenue looks to be quiet during the remainder of the year and really into late February. We expect normal and easier access throughout the next two weeks. Some of this will depend on the weather, but the outlook is quiet on that front.
UPDATE: The Huron Avenue Exit from I-94 is REOPENED for those approaching from the west.
Looking Ahead
We expect to hear the details about the soon-to-arrive signal light at 29th Avenue. This is a positive addition providing a safe crossing option at University Avenue for pedestrian traffic. It has been discussed as being added early in 2012, so we’ll let you know as soon as we hear!
We’re also encouraging sidewalk extensions and improvements along the west side of 29th Avenue between Textile Center and the surface parking lot just off 4th. We expect this to take a good amount of energy to get it into the plans and establish a timeline.
|